This year’s Thorn Creek Habitat Improvement Project wrapped up on Sunday, August 4, 2019 with the planting of 200 live stakes of native riparian shrub species on the newly installed habitat devices. During the two week construction period, work crews from the CWA, PA Fish and Boat Commission, Western Pennsylvania Conservancy, CN Railroad, Penn Township, and Phil Hay and Sons Excavating installed over 1400 feet of instream habitat devices. These devices included 25 sections of mud sill, 3 root wad deflectors, 7 log frame deflectors and a log cross vane. All of these devices will serve to stabilize the stream bank, provide overhead cover, and move pressure from the primary water current away from eroding stream banks.